Home Projects Data center Renovation

Data center Renovation

The issue

The customer has a 24/7 running datacenter that serves branches and different points of sales all over Saudi Arabia.
The datacenter room, however, was not physically secured and had some power outage issues.

The Solution

We built a dependable, highly-secure datacenter with standby power availability.

The key benefits

Promoting the availability of their data center and services, improving the power and connectivity systems, and having fully documented systems architecture.

Challenges

Very narrow downtime slot, and the customer's services should remain uninterrupted. We had very strict working hours and the equipment needed special handling.

Details

We executed the whole project along with the installation of a whole data center equipment and all power, cooling and physical security systems with only twice six hours downtime.

DC_B